□ Conducted before building demolition report
□ Request to asbestos investigation agency: 1 day for sampling, 5-10 days for analysis
□ Analysis results must be attached to building demolition report
□ Authority: District office architecture department – Online application
□ 3 days before scheduled demolition
□ Online (SEUMTER) report attachments
– Demolition contract, asbestos analysis certificate
□ Authority: Regional office of Ministry of Employment and Labor, 5 days required
□ Conduct asbestos removal before building demolition
□ Report to Ministry of Employment and Labor after completion
□ Authority: District office
□ Register in Allbaro System
□ Authority: District office architecture department
□ Within 30 days after demolition completion
□ Contact relevant agencies for electricity, water/sewage, wastewater, gas, etc. before disconnection